January 2026 Construction Activity:
Upcoming Activity for January:
- Continue alley road construction between 15th Ave W and 16th Ave W.
- Miscellaneous concrete pours. Concrete trucks will be staged in closed lane of 15th Ave W.
- Install of underground building utilities onsite and offsite.
- Structural steel erection. Steel trucks will be staged in closed lane of 15th Ave W.
Sidewalk and road changes occurring in January:
- Daily, closure of the west travel lane on 15th Ave W SB. Sidewalk will remain open. Flaggers will be present to assist with pedestrian traffic.
Contact us
For any traffic-related questions, contact Superintendent Dan Hemmington at DanH@sellen.com or 206.396.0210.
For other questions, concerns or wish to be added to the bulletin distribution, email our project team at: thepalms@sellen.com.

Pickle at the Palms is a new indoor pickleball destination arriving in summer of 2026. Located on 15th Avenue West, just south of the Ballard Bridge, Pickle at the Palms has been designed and will be built from the ground-up to provide a player-focused pickleball experience.
For more information, visit:
PickleatthePalms.com