Bellevue 600 Construction Updates
October 2023
ACTIVITY
In October, the following work will be in progress at the Bellevue 600 project:
- Saturday, October 7 – Sunday, October 8: On these days, there will be crane jumping activities happening for two of our tower cranes between the hours of 7:00 a.m. and 6:00 p.m. Trucks will be staged on 110th Avenue and north of the project inside the fence.
- Saturday, October 14: The road will be closed on 10th Avenue NE from NE 6th Street to mid-block of 108th Avenue NE between the hours of 5:00 a.m. and 6:00 p.m. for hoisting of equipment needed to complete the mass excavation work.
- Pedestrians are being rerouted due to sidewalk closures adjacent to the site on 108th Avenue NE, 110th Avenue NE and NE 6th Street. Please refer to the map for more details.
- Underground street improvements on 108th Avenue NE and 110th Avenue NE will continue this month.
- To facilitate construction activities on the project, the team will be shifting traffic on 110th Avenue NE. Southbound traffic control measures will be in place Monday through Friday.
- Mass excavation work on Phase 2 will continue in October. Traffic along 108th Ave. NE will increase as this activity progresses.
- The City of Bellevue started construction in mid-May at the intersections of 110th Avenue NE and NE 6th Street and 108th Avenue NE and NE 6th Street. While this activity may impact traffic flow around the job site, it is not related to Sellen’s ongoing work on the Bellevue 600 project. Updates related to the work in these two intersections will be communicated by the City of Bellevue.
Questions or concerns? Contact us anytime and we’ll get back to you as soon as possible.
Project Email Inbox: bellevue600@sellen.com

Construction Bulletin Archive
- February 2021
- March 2021
- April 2021
- May 2021
- June 2021
- July 2021
- August 2021
- September 2021
- October 2021
- November 2021
- December 2021
- January 2022
- February 2022
- March 2022
- April 2022
- May 2022
- June 2022
- July 2022
- August 2022
- September 2022
- October 2022
- November 2022
- December 2022
- January 2023
- February 2023
- March 2023
- April 2023
- May 2023
- June 2023
- July 2023
- August 2023
- September 2023
- October 2023
About The Project
The Bellevue 600 project is a new office tower in Bellevue. Early site work is now underway. Updates will be sent out on a monthly basis or 72 hours prior to any significant construction activity requiring additional closures. Click here to subscribe to future project updates.
Connect