Bellevue 600

Bellevue 600 Construction Updates

May 2022

ACTIVITY

In May, the following work will be in-progress at the Bellevue 600 project:

  • Pedestrians are being rerouted due to sidewalk closures adjacent to the site on 108th Avenue NE, 110th Avenue NE and NE 6th Street. Please refer to the map for more details.
  • To facilitate substructure activities on the project, the team will be shifting traffic on 110th Avenue NE. Utility work will continue to take place on 110th Avenue NE through June 2022. Traffic control measures will be in place daily to help reroute northbound and southbound traffic.
  • Periodic construction activities will be taking place on the sidewalk adjacent to The Bravern along 110th Avenue NE. Pedestrians access will be accommodated around work activities.
  • Pending approval from the City of Bellevue, Sellen will be installing a tower crane base on Saturday, May 21, which will require full closure of the section of 110th Avenue NE between NE 6th Street and NE 8th Street. More information about this activity will be communicated the week of May 16.
  • Pending a noise variance permit from the City of Bellevue, the team will be erecting a tower crane on Saturday, June 4 and Sunday, June 5 from 7 a.m. to 8 p.m. More information about the tower crane installation will be communicated the week of May 30.
  • Bellevue Corporate Plaza demolition activities have commenced. Demolition work of the concrete structure will occur Monday through Thursday, between the hours of 7 a.m. to 5:30 p.m. This work will contribute to an increased level of construction noise. Fridays will be reserved for normal construction activities during normal work hours.

Questions or concerns? Contact us anytime and we’ll get back to you as soon as possible.

Project Email Inbox: bellevue600@sellen.com

Map Thumbnail

Download Construction Map PDF

Construction Bulletin Archive

About The Project
The Bellevue 600 project is a new office tower in Bellevue. Early site work is now underway. Updates will be sent out on a monthly basis or 72 hours prior to any significant construction activity requiring additional closures. Click here to subscribe to future project updates.

Connect