Bellevue 600 Construction Updates
April 2024
ACTIVITY
In April, the following work will be in-progress at the Bellevue 600 project:
- Saturday, April 6 – Sunday, April 7: On the weekend of April 6-7, the Bellevue 600 team will be placing concrete for a new mat foundation. As a result, the road on 108th Avenue NE will be closed between NE 6th Street and NE 8th Street between the hours of 2 a.m. on Saturday, April 6 and 12 a.m. on Sunday, April 7. The roads are scheduled to reopen at 12 a.m. on Sunday, but construction activities are scheduled to continue on site until as late as 7 p.m.
- Saturday, April 20 – Sunday, April 21: There will be crane jumping activities on one of the tower cranes between 7:00 a.m. and 6:00 p.m. This work will be completed within the job site fencing on 110th Avenue NE.
- Pedestrians are being rerouted due to sidewalk closures adjacent to the site on 108th Avenue NE, 110th Avenue NE and NE 6th Street. Please refer to the map for more details.
- Underground street improvements on 108th Avenue NE and 110th Avenue NE will continue this month.
- To facilitate construction activities on the project, the team will be shifting traffic on 110th Avenue NE. Southbound traffic control measures will be in place Monday through Friday.
- Concrete placement activities on Phase 2 will continue in April. Traffic along 108th Avenue NE will increase as this activity progresses.
Questions or concerns? Contact us anytime and we’ll get back to you as soon as possible.
Project Email Inbox: bellevue600@sellen.com
Construction Bulletin Archive
- February 2021
- March 2021
- April 2021
- May 2021
- June 2021
- July 2021
- August 2021
- September 2021
- October 2021
- November 2021
- December 2021
- January 2022
- February 2022
- March 2022
- April 2022
- May 2022
- June 2022
- July 2022
- August 2022
- September 2022
- October 2022
- November 2022
- December 2022
- January 2023
- February 2023
- March 2023
- April 2023
- May 2023
- June 2023
- July 2023
- August 2023
- September 2023
- October 2023
- November 2023
- December 2023
- January 2024
- February 2024
- March 2024
- April 2024
About The Project
The Bellevue 600 project is a new office tower in Bellevue. Early site work is now underway. Updates will be sent out on a monthly basis or 72 hours prior to any significant construction activity requiring additional closures. Click here to subscribe to future project updates.
Connect